Topics in this domain

RACI and Escalation

Ownership and accountability · 1 min read

RACI for risk activities

RACI example: assess risk, choose treatment, implement controls, accept residual risk, approve risk policy, with one Accountable per row.

The four letters

LetterMeaning
RResponsible: does the work
AAccountable: answers for the result (exactly one person)
CConsulted: gives input beforehand
IInformed: told afterwards

Escalation paths

Escalation layers: control owner, risk owner, steering committee, executive management, board.

Escalation should be triggered by thresholds agreed in advance, so it isn’t a personal fight. It’s part of normal governance, not a sign of failure.

Example. A KRI for unpatched critical servers turns red. The agreed path sends it to the risk owner the same day and to the steering committee if it isn’t recovered in 30 days. When it wasn’t, the committee approved an emergency patch window.

How the exam asks about it

If the question asks…The answer is usually…
How many Accountable per activityExactly one
Purpose of a RACIClarify roles and avoid gaps or overlaps
What triggers escalationAgreed thresholds
Owner ignores an overdue high riskEscalate through the agreed path

In short

  • RACI shows who is Responsible, Accountable, Consulted and Informed for each activity.
  • Each activity has exactly one Accountable person.
  • Escalation paths define how far a risk travels based on agreed thresholds.
  • Escalation should be triggered by thresholds agreed in advance, not personal judgement alone.
  • Escalation is part of normal governance, not a sign of failure.

Exam traps

  • Two Accountable people for one activity.
  • Escalating directly to the board, skipping the risk owner.
  • Not escalating because it might upset the owner.
  • Escalation paths with no thresholds.

Slides

Click the slide and use the arrow keys. F toggles full screen.

CRISC · Domain 3 · Ownership and accountability

RACI and Escalation

How a RACI chart makes responsibilities for risk activities clear, and how agreed escalation paths and thresholds move risks to the right decision-makers in time.

1 / 7